Knowledge Center > Industry Articles
Efficacy of Partnering on the Woodrow Wilson Bridge Project: Empirical Evidence of Collaborative Problem-Solving Benefits
Lee L. Anderson, Jr., P.E, M.ASCE, and Brian D. Polkinghorn, Ph.D.1
About
This article examines the large body of partnering rating data collected during eight-plus years of partnered construction contracts on the Woodrow Wilson Bridge replacement project. The authors report that partnering efficacy, as measured by “collaboration,” was not predetermined by bid results or regional/national distinctions between construction contractors. The data show that good partnering is strongly associated with team satisfaction with budget and schedule results. The correlation among these indicators is not “proof” of the effectiveness of partnering. However, had the analysis shown negative correlations where positive correlations were expected, enthusiasm for construction partnering would certainly have suffered a blow.

Subject Headings
  • Partnerships
  • Construction management
  • Contract management
  • Project delivery
  • Human factors
  • Communication
  • Conflicts
  • Dispute Resolution

    Introduction
    Construction partnering is not new – it has been a popular strategy since the 1980’s for minimizing and managing conflict on construction projects. Usually initiated by owners, partnering requires an investment of both money and staff time. Hence, especially in times of limited resources, owners want to know whether partnering “works.”

    The quest for affirmation of partnering efficacy is nearly as old as the practice of partnering. One informative early study (Lowe, 1994) used questionnaires to investigate partnering use in Navy construction offices. Lowe reported that, “subjective results are all but unanimously in favor of partnering,” but that “the objective analysis is inconclusive.” Owners and contractors always have been anxious for some quantitative demonstration that their investment in partnering is producing a positive return. However, partnering outcomes are not easily measured. Commonly, participants report on the issue of how “satisfied” they are with the partnering process, although with what they are satisfied often remains a mystery. More importantly, the links between the process and the eventual outcome – a more critical topic in our estimation – are rarely examined empirically. Perhaps the participants “felt like a team,” but did partnering improve schedule performance? Did partnering save money?

    The answers to questions like these are hard to measure for at least two reasons. First, only rarely will a construction contractor tell the owner what profit or loss the firm experienced on a contract. That information is business-sensitive. If told that the contractor made a lot of money, the owner might feel that he paid too much for the work. If the contractor lost money, the contractor would not want his or her competitors to know. So, information about dollar results is not publicized.

    The effect of partnering is also hard to analyze because the outcomes of an individual construction project are so heavily affected by external factors. Regardless of whether a job was partnered or not, bad weather might delay completion. Unexpected material cost inflation may skew budget results. Differing site conditions might generate legitimate change orders. There is no way to have a perfectly controlled experiment – to work exactly the same job with and without partnering – because each job will encounter a different set of external conditions, invalidating the hoped-for “pure experiment.” We are therefore left to less precise, quasiexperimental models of inquiry. In the nature of construction, all contracts, partnered or otherwise, will be subjected to forces and conditions outside our personal control which can lead to scheduling delays and cost challenges. If not properly managed, these forces and conditions can also create a secondary source of conflict among partners.

    Owners with large construction programs comprising many individual contracts have had some success in measuring partnering outcomes by looking at aggregated data across their programs. The Arizona Department of Transportation found the welcome news that, after instituting partnering across the board, contract claims fell from 60 in 1991 to less than one per year. After 2003, Arizona DOT experienced no contract claims, and they abolished their claims department (Young, 2009). The Oregon Department of Transportation performed a programwide analysis in 2002, showing many advantages of partnering based on anecdotal reports (Rogge, et.al, 2002); it was based on a survey of 132 state employees and 42 contractors who had previous experience with partnering. The Maryland State Highway Administration commissioned a study of its partnering process and program; part of this study took data from various isolated internal databases and linked it to a separate SHA partnering database. The study found that an increase in the use of partnering correlated with a decrease in claims. (Polkinghorn, et. al, 2006). While this study found it difficult to control for the impact of external forces (extraneous or intervening variables) due to the nature of the data available, the results pointed to a genuine impact of partnering on reducing post-construction claims.

    Results like this, when properly examined using statistical analysis, serve many useful purposes. They allow researchers to examine whether or not certain variables impact partnered construction projects, whether extraneous variables impacted the results, and to some degree suggest what components of partnering may have the greatest impact on critical measures. Empirical research also provides clarity and may help steer future use of the partnering process under specific project, site, and local political conditions.

    Many studies that focus on the experience of individuals within the partnering process, typically measured in terms of process elements and associated degrees of satisfaction, go no further in exploring statistical relationships pertaining to core variables impacting the project. While these findings are important for those involved in managing collaborative decision-making processes, they may not encompass a holistic or systemic approach to the study of partnering on the site or with community stakeholders. Likewise, many partnering studies that examine the process rely on findings that are limited to the internal workings of the process and are supported by descriptive testimonials and/or prescriptive recommendations. The study at hand largely escapes these limitations.

    This article presents a quantitative analysis of partnering outcomes resulting from the Woodrow Wilson Bridge (WWB) program. The WWB program replaced the Interstate 95 bridge crossing the Potomac River at the Maryland/Virginia state line near outside Washington, D.C., and reconstructed four major interchanges, two on each side of the river. Program costs totaled $2.5 billion (about $1.5 billion in construction alone). The program comprised 19 separate, major construction contracts awarded by two owners, the Maryland State Highway Administration and the Virginia Department of Transportation. Most of the construction was performed during the years 2001-2009. One large contract (VB-2/3/6) is still underway at this writing, and a final smaller contract is still to be awarded. With these minor exceptions, for the purposes of this article the program may be considered complete.

    The WWB program presents a unique opportunity to study partnering outcomes. All of the major contracts were partnered, so admittedly there was no “control” on the program’s application of partnering. However, the program was characterized by many factors that permit insightful contract-to-contract comparisons to be made. One factor is simply the breadth and depth of an exceedingly large quantity of data, described in detail below, that was captured over eight consecutive years. Another is the constancy of leadership on the owner side: one person in Maryland and one person in Virginia were in charge of their respective agency’s efforts for the vast majority of the period of observation. These individuals set the tone for their subordinates, so there was less variability in owner-side priorities across the 19 WWB contracts than would have existed, say, if the contracts had been administered by separate districts in a state highway department. The individual contracts ranged in dollar value at award from about $3 million to $236 million.

    The WWB program was a remarkably successful endeavor. As a public infrastructure megaproject completed on time, with only three-percent budget growth over eight years – resulting in a beautiful bridge and major improvements to traffic flow – it was heralded by the public and lavishly recognized with industry awards. Notably, one of the contracts received a 2009 Marvin Black Award for Partnering from the Associated General Contractors of America. All of the 19 contracts were successful, although the participants would readily agree that some contracts proceeded better than others did. Some were more or less profitable, more or less timely, or proceeded with a greater or lesser sense of teamwork and cooperation. The collective outcome is remarkable, given the scope of the program and the countless issues and problems that could have easily derailed the entire project. The aggregate success of the program could well be attributed to the consistent application of insights articulated in the standard conflict resolution literature (Anderson & Polkinghorn, 2008). None of these insights resonates quite so strongly as the Maryland WWB Project Director’s mantra (lesson #10 in the cited work) that, “We all succeed together.”

    This internal evaluation of the vast partnering rating data collected on the WWB program shows – in quite satisfying ways – that partnering “works.” For example, the analysis here examines the relative effectiveness of partnering on the 19 contracts as a function of bid results. [Contracting is, in essence, a give-and-take process, in which people bring things to the table to exchange. Likewise, negotiators create value and incentives, and they claim value and rewards. The construction industry is no different, except that the end-results of the give-and-take process are a tangible structure or facility on the job site.] So, had the analysis shown that when contractors left a large amount of money “on the table” at bid time, the team reported lower partnering satisfaction than in situations where the winning bids were just slightly below the next competitors’ bids, one might surmise that the partnering effort had been wasted. If only contractors with full wallets make good partners, why bother with partnering? Happily, this is not the result, and there must be a more meaningful explanation that encompasses parts of the current findings. The analysis here also examines whether regional contractors made better “partners” than national contractors, finding only a modest correlation with geography.

    The authors also look at how reported effectiveness of issue resolution correlated with the softer human-performance factors involved in partnering, and how self-reported results for schedule and budget correlated with partnering effectiveness. Showing objective schedule and budget gains attributable to partnering would be the “gold standard” – the object of nearly every other previous analysis of partnering outcomes. However, because of the externalities explained above, the self-reported schedule and budget outcomes are probably as valid as any. Success at issue resolution is important as a postulated causal link between better schedule/budget performance and the human performance factors.

    With the large body of WWB program partnering data available, the authors are able to examine three other hypotheses as well. First, this article explores whether effectiveness at managing community relations correlated with good schedule performance (finding a moderate association). Second, the paper examines how the partnering rating indicator for safety matched actual safety experience – to some extent, simply as a means to examine whether the partnering raters were “paying attention.” [The answer: maybe.] Finally, the article delves into a partnering commonplace: that having construction company senior managers attend monthly partnering follow-up meetings is a secret to partnering success. Interestingly, the data show a negative correlation for this hypothesis.

    Methodology
    This study draws on the entire body of partnering ratings submitted by participants in each of the 19 WWB contracts. The rating process was described in detail in another article (Anderson, et.al, 2006). Briefly, the participants would visit the WWB program website (www.wilsonbridge.com) before each partnering follow-up meeting, finding there a dedicated rating form accessible by a username and password. To rate each indicator, the participant would select a score (from 1 to 4 or “I don’t know”) with a mouse click, type in any comments he or she wished to offer, and submit the form. A “4” was consistently the best score, and a “1” was consistently the lowest score. The WWB program partnering coordinator or assistant would receive an e-mail generated by the internet server for each rating and tally the results on a spreadsheet for presentation. Ratings were collected in the days immediately preceding each partnering follow-up meeting for discussion at the current meeting. In essence, gathering rating scores and comments served as a means to flag current issues as well as to provide an early warning of potential problems.

    This rating process was done for 354 follow-up meetings. The meetings were attended by over 8800 people [counting the same people many times, of course]. Average attendance was about 24 at each meeting. Not every person provided a rating for every meeting, and team participants were welcome to rate even though they could not attend a particular meeting. The total body of rating data represents an estimated 6,000 individual rating form submissions. In comparison to most construction projects, the number of meetings, participants involved and subsequent rating forms is incredibly large. Also, the fact that these data were collected over an eight-year period provides a means of observing partnering performance within the project over an extended period of time.

    The rating criteria and the narrative meanings of each score were customized for each of the 19 contracts. The rating categories were chosen to support analysis of achievement of the particular objectives which each contract team had agreed to include in its charter at the partnering kick-off meeting. This means there were a variety of measurements taken on different contracts, and that complicates comparison of data across contracts. Nevertheless, many of the rating categories and score meanings were common among the contracts. [For Maryland construction contracts, certain rating elements were prescribed to support the State Highway Administration’s business plan.] Thirteen categories were scored by at least eight of the 19 contracts, and six were scored by all 19. Table 1 refers.

    For purposes of this study, the authors create a collective indicator after the fact to capture the softer, human-performance side of the partnering effort. Called “collaboration,” this indicator is the sum of the average Teamwork, Communication, and Cooperation scores for each contract at each meeting. That is to say, the “collaboration” score attempts to smooth out anomalies in teamwork or communication or cooperation scores by presenting a single indicator as a representative of how well the individual contract team was succeeding in working together. It also allows for comparison of human factor problem-solving across various contracts. This also then allows the researchers to examine contracts in regard to measures such as schedule and budget. The authors hypothesize that contracts presenting high mean scores for “collaboration” should present outcomes consistent with a high level of human factor cooperation.

    The theoretical literature on collaborative problem solving, as it impacts the core characteristics of partnering, can be summed up in one sentence. “If the primary stakeholders can interact in an open setting while focusing on interest-based dialogue, then these conditions substantially aid in the search for and acquisition of mutually beneficial outcomes.” The link between principled negotiation and problem solving in construction partnering has been highlighted in previous research on the WWB project (Anderson and Polkinghorn, 2008).

    Statistical Method
    The observations and analyses presented below result from performing a statistical correlation test between data sets. This was done using the CORREL function in Microsoft Excel. Where an array contains empty cells, those values are ignored. A score of +1 indicates a completely positive correlation between the variables measured. A score of 0 indicates no relationship, and a score of -1 indicates a complete negative correlation. Interpreting the meaning of the numbers in between could employ more sophisticated methods than are appropriate for the purposes of this paper. Jacob Cohen (1988) offered a simple scale of small, medium, and large correlations which the authors adopt here. He characterized a “small” correlation as the range -0.3 to -0.1 or +0.1 to +0.3. Cohen’s “medium” correlation is the range - 0.5 to -0.3 or +0.3 to +0.5, and his “large” or “big” correlation is -1.0 to -0.5 or +0.5 to +1.0. The authors often use the word “strong” below to mean “large” or “big.”

    In the case of the partnering data, as will be seen below, the data sets had few outliers. Hence, the correlation coefficient is considered an appropriate tool for gaining insight about these partnering measures. However, as is often said, “Correlation does not imply causation.” Statistical correlation is no guarantee that one set directly causes the data in the corresponding 7 set. In the analysis below, the opposite of this common wisdom is more apt: if we believe partnering “works” in some way, it would be revealing (and disheartening to partnering boosters) if the expected positive correlations were negative or only weakly positive.

    The 19 construction contracts included in this study run the gamut in size (as mentioned above), duration (from about 18 months to over five years), and complexity. In the charts below, each contract is identified on the X-axis label by a two-letter prefix and a number or short series of numbers. Contracts labeled “BR” were those for the bridge superstructure; the “VA” contracts were for the U.S. Route 1 interchange in Virginia; the “VB” contracts were for the Telegraph Road interchange in Virginia; the “MA” contracts were for the I-295 interchange in Maryland; the “MB” contracts were for the Maryland Route 210 interchange; and the “MM” contract was a larger environmental mitigation contract in Maryland.

    Observations and Analysis: Partnering versus Bid Results
    The first question to ask is whether partnering outcomes are “fixed” on bid day. It would be reasonable to suspect that a construction contractor who wins a contract with a bid that is far below his nearest competitor might enter the contractual relationship with much regret and trepidation. Those feelings could color the relationship and make it well nigh impossible to enjoy a fruitful partnership between owner and contractor. Indeed, if his budget were stretched too thin, one might expect the contractor to be looking for change orders at every opportunity to recover his opportunity to make a profit. In such a situation, would partnering matter? Or, would the contractor sink into the psychological phenomenon called “buyer’s remorse,” where one realizes he has entered into an agreement that is quite unfavorable to his interests?

    The authors look at this question in two ways. First, we plot the collaboration score defined above for each contract against the percentage by which the winning bid fell below the next lowest bid. Winning margins varied from a miniscule 1.05% to a hefty 19.90%. One contract, VB-4, had only one bidder. A negative correlation would be expected, with higher percentage left “on the table” corresponding to a lower collaboration score. Indeed, the correlation is negative, but at a small -0.372, it is far from strong. Figure 1 plots the data.

    Looking at the same question in another way, the authors represent the bid results as a percentage of the next group of bids (up to three) above the low (winning) bid. A higher percentage meant that the winning bidder was closer to the collective pricing wisdom of up to three other competitors, not just the next higher bidder. These percentages varied from just 77 percent to over 97 percent. The correlation coefficient is again negative, as expected, but scarcely different from the correlation against the winning margin at a small 0.382. Figure 2 shows the results. The one anomalous data point (not figured in the correlation coefficient) represents there having been only one bidder for contract VB-4.

    Regional versus National Firms
    It would be reasonable to forecast a priori that a regional construction company would perform better as a partner for a state highway agency than would a national construction company. A regional firm, one whose primary business is conducted within a few states localized within an easy drive, might very well have worked with a particular state highway agency before. Personal relationships at the top might have been cultivated over many years of working together. The regional firm would have every incentive to please its regional clients, especially as the selection for major construction services moves away from automatically choosing the lowest bidder to choosing the firm which can convincingly offer the best value to the owner. One would expect the regional firm to be a stellar partner with the most to gain as well as the most to lose.

    Conversely, one might expect that a large construction firm which is bidding jobs coast-tocoast might never have worked with a particular agency before, would have no existing relationships to nurture, and could reasonably not expect to work for the same owner again for many years. One could expect the national firm to be a good “partner” only when it suited his or her advantage. Mitigating this to some extent, one might assume that the lack of personal contact would be substituted for by national reputation. [Before moving on, it is worth noting that the psychology here is complex: when people have a personal relationship with others, as might be the case with the regional firm, they have more at stake as they are not part of an aggregate or large and ambiguous entity but a person who can be easily identified and held accountable. Likewise, social psychological research tends to suggest that when individuals feel they are part of a larger group and have a sense of being anonymous, they misbehave more so then when they are singled out and identified.]

    Twelve different firms or joint ventures performed the 19 contracts on the WWB program. Classifying these entities as “regional” or “national” in their outlook was sometimes a matter of judgment, because a joint venture often represented a combination of a local firm with an out of-town partner. Table 2 shows the classification that the authors adopt; generally a joint venture lead by a strong local partner is classified as “regional” even if they had brought aboard a national partner.
    The analysis is performed as follows. The authors assign a value of “1” for a regional contractor and “0” for a national contractor. The resulting array for all 19 contracts is then correlated with the collaboration score (just as defined above). The computed correlation coefficient is 0.419 – a “medium” strength correlation by the Cohen characterization above. With all of the seemingly logical reasons why a regional contractor should be a better partner than a national contractor, it is instructive to see only a medium-strength correlation coefficient come from the analysis. And, while its collaboration score ranked just number 9 of the 19 contracts, the BR-3B contract – led by a national firm (Granite Construction Company, Inc.) – was the one selected to receive the 2009 Marvin Black Award for Partnering from the Associated General Contractors of America.

    From the data and the anecdotal evidence cited, the authors infer that the “national” or “regional” status of the prime contractor does not predispose construction partnering to be less or more successful. While the authors were able to construct a “collaboration” variable (see page 5 above) to examine the soft side of the data, the same has not been accomplished in regard to status of the firms of joint ventures. Therefore, a number of alternative reasons or contributing variables, not directly measured here, are tantalizing as a subject for future research. One variable that might temper this finding could be the status of the project. WWB was arguably a high profile project. Both regional and national contractors could appreciate the visibility and reputation that their efforts on the WWB project would earn in the public eye and with national decision-makers. Another related avenue of exploration could be the operational strategy of a firm, or a joint venture understanding among partners, in regards to partnering. Likewise, the character of a firm’s management staff would be a potential source to explore, as some construction firms, regardless of regional or national character, are adept at partnering, understand its principles and know how collaboration can impact outcomes. Conversely, other firms take a more cynical or mechanistic view of partnering and see it as “hoop to jump through” or a “box to check” and not a way of doing business. Even more troubling are firms who are sometimes accused by others as viewing partnering as a means of extracting · American Bridge/Edward Kraemer & Sons National · Corman Construction Regional · CK Constructors (Corman – led JV) Regional · R.R. Dawson Bridge Company National · John Driggs Company Regional · Glover Construction Regional · Potomac Constructors, LLC National · Shirley Contracting Company, LLC Regional · Skanska USA Civil Southeast National · Tidewater/Kiewit/Clark Joint Venture National · Virginia Approach Constructors (Granite – led JV) National · G.A. & F.C. Wagman Construction, Inc. Regional Table 2. National vs. Regional Contractors concessions not stated in the contract. Delving into variables of this nature would be highly subjective and perhaps impossible to examine convincingly.

    Collaboration versus Issue Resolution
    One rating criterion reflected on all 19 of the WWB construction partnering rating forms was issue resolution. Any experienced construction practitioner would regard the ability to have issues resolved in a timely, interest-based manner as a key element of a project’s success. Sometimes a construction contractor will encounter a conflict on the blueprints: one drawing shows something one way and another shows it the opposite. Or, the blueprints and the specifications may differ. Or, an unexpected obstacle is discovered when soil excavation begins. The list of possible issues arising on a construction project is seemingly endless. Ideally, many issues are resolved right on the spot, in consultation between the superintendent and chief inspector, or between the contractor’s project manager and the owner’s resident engineer. Issues requiring technical analysis may be returned to the engineer-of-record as a “Request for Information” or “RFI” to get an engineering answer. In any case, timely resolution is important. Workers may be unable to divert to another task, or critical materials and equipment may sit unused or idle, until the issue is resolved.
    As might be expected, the WWB partnering analysis shows a very strong positive correlation between the collaboration indicator and the issue resolution score: 0.947. Figure 3 charts the data.

    This outcome confirms what one would expect: a strong association between good partnering (as represented by the composite collaboration score) and the all-important issue resolution performance. This virtual truism works whichever way it is postulated: because collaboration is better, issues are resolved more effectively. Or in reverse, because issues are resolved more effectively, the collaboration is regarded as better. They mirror one another. The most plausible reason is the ability to establish the conditions that reinforce effective communications: collaborative problem-solving that supports the notion of teamwork. Underlying these composite scores are the notions of honesty, trust, and the parties being held accountable to one another.

    Collaboration versus Budget
    As explained above, it may be asking too much to demonstrate that partnering has a salutary effect on whether the contractor makes a profit or not, and whether the final price tag stays within the owner’s budget. Many external factors can affect the budget outcome which are beyond the ability of an effective partnering program to influence. On the WWB program, eight of the 19 contracts tracked a “budget” indicator. A typical “budget” criterion rating scheme (as used for this example on the $236-million contract VB-2/3/6) read as follows:

    “Owner and Contractor are both meeting budget expectations:
    Score 1: Overspent-cannot recover
    Score 2: Overspending-must compensate
    Score 3: Near target
    Score 4: Doing better than expected”

    The adjectival descriptions assigned to each numerical rating score were thus aimed at a “3” being the accepted score if the project budget was on track for both owner and contractor. Generally, neither side had good visibility over the other’s budget situation, so owner raters would score how the owner was doing, and contractor raters would base their ratings on contractor financial projections. Generally, stakeholders not familiar with the budget situation of either owner or contractor would simply mark “I don’t know.”

    Even with partners not knowing all the budgetary details, Figure 4 shows a strong positive correlation of 0.842 between the collaboration indicator described above and the average budget scores assigned on the contracts that chose to track this criterion.

    The authors, while not surprised to see this result here and above on issue resolution, want to maintain a critical view alá Popper’s “falsification” process of working to prove your own hypothesis wrong. In other words, Popper says a good researcher doesn’t simply accept the conclusion, especially if it is positive, but seeks to refute it in order to find a more encompassing explanation of the results. In this case, this strong positive correlation does not necessarily “prove” – but maybe “tends to suggest” – that well-partnered contracts produced better budget outcomes. However, our critical view leads us to acknowledge the possibility that the reverse phenomenon may have been operative instead: on contracts where the budget was being met, perhaps the partnering team members found themselves under less stress and hence behaved as better team members, communicated better, and cooperated more with their counterparts. Still, had a weak or negative correlation been manifest from the WWB data, that result would have been quite disheartening for partnering advocates.

    As an aside, notice the relatively lower average “budget” score for the award-winning BR-3B contract (it was a 2.93). It is instructive to know from one author’s personal reminiscence that the parties recognized the budget difficulties on that contract, but in their discussions they acknowledged that the collaboration which was occurring kept the budget difficulties from becoming considerably worse. The teachable idea from this example is rather simple: if partners know there will likely be problems ahead, they should continue to communicate and solve problems as a team as clearly and often as possible. That is, they should do so if there is trust. Without trust, one could be wiser to adopt the opposite tactic: namely, to withdraw and run for cover while placing blame on others.

    In fact, among all these findings so far, one has to consider the possibility of a self-fulfilling prophesy coming into play. If we are predisposed to work well with others (high collaboration), then we are predisposed to give others the benefit of the doubt when something goes wrong and to chalk up any problems to external conditions rather than to personal characteristics. Likewise, if the working relationship is not good, the opposite often occurs. We do not give the partner the benefit of the doubt; we chalk up the problem to an internal flaw in their character, or we attribute their actions to some evil intent.

    Collaboration versus Schedule
    All 19 of the WWB contracts had a partnering rating indicator to track how well each contract was doing at conforming to its established schedule. Typically, the adjectival descriptions for each score of 1 to 4 were highly customized. On contracts with incentive milestones (where the contractor could earn a bonus payment for meeting certain target dates), the “schedule” rating scheme focused on the likelihood of his meeting the incentive dates. Other contracts did not have incentive milestones, so the adjectival scoring was somewhat different. It is also relevant to observe, from one author’s reminiscence, that some raters gave greater weight to the process of submitting and maintaining the required critical path method schedule under this criterion, while other raters focused exclusively on the results.

    Notwithstanding these caveats, it is at least somewhat informative to see a strong positive correlation between the average collaboration scores and the average “schedule” scores. Figure 5 charts the result, displaying a correlation coefficient of 0.682.

    Many of the same things said above about “budget” could also be said about “schedule.” The substantial positive correlation does not “prove” that well-partnered contracts produce better schedule outcomes. On contracts where the schedule was being met, perhaps the partnering team members found themselves under less stress and hence behaved as better team members, communicated better, and cooperated more with their counterparts. However, partnering advocates can take heart that a weak or negative schedule correlation is not manifest from the WWB data.

    Community Relationships versus Schedule
    In addition to addressing the basic questions about the efficacy of partnering discussed above, the voluminous body of WWB partnering data allows the authors to explore some pertinent sidebar issues. One interesting issue is how the relationship between the partnering team and the community at large – “outside the fence” – may have been associated or not associated with schedule performance. It would be reasonable to surmise that an antagonistic relationship between the project team and the community would lead to schedule delays. Opponents might have found ways to raise continuing objections to the project which would have impeded its progress. Conversely, delays in project completion might be associated with a decline in public goodwill towards even a project which the public welcomed.

    There are countless methods by which the public can impact a construction project. These range from attending and taking over public meetings, engaging state and federal agencies in an attempt to enforce particular regulations or laws that meet their agenda; demanding meetings with project managers; writing letters to the editor, giving interviews on the radio and public access television, organizing petition drives, calling elected officials and demanding that they investigate constituent complaints, or filing lawsuits and requesting injunctions – to name just a few. There are also countless reasons why members of the public might object to construction projects. Some might be: environmental justice concerns over disproportionate impact to minority communities, destruction of historical sites, protection of sensitive aquatic or forest ecosystems, impact to threatened or endangered species, aesthetic disputes, and increases in “noxiants” such as noise and air pollution. Members of the public can also engage in disputes on construction projects because of more abstract political and ideological agendas. Disputes of this type, while they may be unfounded, also take time and resources to address. With NIMBY (“Not in My Back Yard) groups ranging from all socio-economic, ethnic, and racial groups to ideologically driven deep ecologist/environmentalists such as BANANAS (“Build Absolutely Nothing at All Near Anything”), the stakes climb even higher. Together the methods by which the public can engage in disputing along with the untold issues and/or (ideological) reasons to do so make for a dynamic and sometimes unstable mixture that can easily disrupt or destabilize a construction project. The results of such disputing can show up in scheduling delays, cost overruns, radical reworking of the project itself or, in some cases, the demise of a construction project altogether.

    Realizing the immense nature of the Woodrow Wilson Bridge Project, it was important for the program to deal effectively with community relations. Nine of the WWB contracts included a specific community relations or public relations indicator within their partnering rating process. Just as there were differences in the adjectival definitions for “schedule,” the adjectival definitions for each numerical score under community relations had differences. Furthermore, different raters easily may have had different interpretations about the substance of this particular criterion. Hence, any conclusion from the correlation between community relations and schedule ought to be treated with particular skepticism. Nevertheless, Figure 6 charts the average scores for community relations and schedule, showing a just-barely-large positive correlation of 0.524.

    The correlation of community relations with schedule suggests that some of the mechanisms discussed above were operational on the WWB project. It is the authors’ mutual sense that the fact that the WWB program generally stayed on schedule had a salutary effect on community relations. This was a more important effect, based on the authors’ anecdotal recollections, than situations where community issues might have posed obstacles to schedule progress. However, so many other factors influenced schedule that it seems unlikely that the positive correlation shown here can demonstrate that community relations were a major driver in schedule outcomes.

    Collaboration versus Company Officer Attendance
    The conventional wisdom among partnering practitioners is that it is very important to have construction company senior managers attend partnering follow-up meetings, along with customer agency senior managers. That way, so the logic goes, the partnering meetings can be genuine problem-solving sessions, and subordinates will be motivated to behave in the collaborative ways modeled by their bosses. In addition, having managers with decision-making authority take part in face-to-face, interest-based partnering discussions should allow for accurate and timely resolution of issues. Interestingly, the pesky WWB partnering data suggest that the opposite is true: less frequent attendance by construction company senior managers is correlated with higher collaboration scores.

    This analysis is conducted as follows. First, the authors identify by name the individuals who were vice presidents or higher in their construction companies and who also attended partnering followup meetings as documented in the meeting minutes. Some contracts had only one vice president (or higher) ever attend a follow-up meeting, whereas some of the large joint-ventured contracts had up to eight. Referring to these populations of executives, the follow-up meetings are coded according to whether any corporate officer had attended. On four contracts, at least one company officer attended 100 percent of the time; on one contract (MM-6), no company officer ever attended a follow-up meeting. On average, 66 percent of the follow-up meetings had one or more company officers present. Then, the percentage of meetings where a company officer attended is compared against the collaboration score for the contract. Figure 7 shows the respective data series, which have a negative correlation of 0.318.

    This negative correlation was surprising to the authors but not necessarily to some practitioners with whom it has been shared. Some explain the negative correlation by observing, “Of course that’s the case: the executives only showed up for a meeting when the job was in trouble. They were managing by exception. If the job was going well—and being partnered well—there was no need for them to show up.” If the folks lower in the organization are doing well, then it is in the best interest of the executives to empower them to work on issues and simply to keep the higher-ups informed. This also makes good business sense, as the adage “time is money” is true, and in this case, “one head is better than two.”

    Inspection of these data suggests further that including the MM-6 contract might have skewed the statistical analysis. Interestingly, that contract was small in dollar value (about $3 million) and had only four follow-up meetings. A company officer attended the initial kick-off meeting but did not come to any of the four follow-up meetings. This contract proceeded very smoothly, and the partnership between the owner and contractor was a great example of “doing it right.” If the MM-6 data are excluded from the analysis, the correlation between the respective arrays remains negative but falls to a weaker 0.126.

    The negative correlation between collaboration and officer attendance data suggests that it is unnecessary for partnering advocates continually to be urging senior managers (on the contractor side, at least) to attend partnering follow-up meetings. Perhaps these managers can just as well decide for themselves when it would be helpful for them to attend. The iconoclast might phrase this implication even more strongly: senior managers should be discouraged from attending partnering follow-ups. Maybe they just get in the way! The advice should be, “Leave the problem-solving to the working-level team members, and just watch from afar.”

    Safety Results versus Partnering Safety Scores
    On the WWB program, all 19 of the partnered contracts kept track of a rating indicator regarding safety. This rating indicator was a companion to the actual accident experience and exposure ratings, which were also recorded concurrently for every contract on the program. Maintaining a separate partnering rating indicator for safety had at least two advantages: it ensured that safety would be discussed at each partnering follow-up meeting, and it gave the raters an opportunity to add insights about safety which the raw safety statistics might not show. Paramount among the latter was the opportunity to add a comment about the safety program in general or a specific incident in particular.

    The adjectival descriptions for the “safety” criterion varied among the 19 contracts. Some partnering teams chose to keep the meanings of the scores from 1 through 4 highly quantitative: they were interested just in measurable results. Other teams chose to describe the meanings of the scores in ways which spoke to the broader effectiveness of the safety program and the zeal with which it was pursued. These teams allowed for the fact that an element of randomness enters into the accident experience on a short duration contract, and they were most interested in seeing that a strong safety program was in place to make the workplace a safer one. Naturally, this variability in definitions makes an overall analysis of the partnering safety data quite equivocal. Nevertheless, it proves interesting to compute the correlation.

    The authors compare the array of partnering safety scores with the final OSHA incidence rate (or “case rate”) on each contract. The OSHA incidence rate, simply explained, is the number of workplace accidents (of more consequence than a first-aid case) that a 100-person workforce experienced in a year. [The 200,000-hour divisor in the incidence rate formula is 40 hours x 50 weeks x 100 workers.] Figure 8 shows the comparison between the average partnering safety scores and contract-long OSHA incidence rates for all 19 contracts. The computed correlation coefficient between these series is negative 0.50.

    Inspection of the data shows one clear outlier: the VB-4 contract had an OSHA case rate of 15.8. VB-4 was a short-duration contract that, unfortunately, experienced more than its share of accidents. The partnering raters recognized the somewhat random nature of this, and scored safety a mid-range 3.51 in the partnering surveys. Without the VB-4 data, the correlation between the two arrays would be a much stronger negative 0.712.

    What can be learned from these data? The direction of the correlation is negative, as should be expected. Higher numerical accident experience records are associated with lower partnering safety scores (where the higher score is always the better score). To that extent, at least, the partnering rater population was answering the surveys in ways consistent with the accident experience which was occurring in the field. Much more than that cannot be learned, however, since there was an element of evaluating safety program strength, rather than accident experience, in some of the individual contract rating schemes.

    Data Discussion
    Planners of the WWB project not only broke a complex project down into incredibly detailed and carefully orchestrated steps, they also set up mechanisms to make sure unforeseen and unintended consequences were identified and managed as early and effectively as possible. Part of that overarching planning process included the foresight to develop and use a sophisticated data collection and tracking protocol on the partnering process itself. The body of data thus collected now allows researchers an empirical means by which to examine process and outcome relationships. The primary benefit of partnering is to prevent and or effectively manage issues. If partnering is such a valuable function as proponents state, then they shouldn’t rely solely on descriptive accounts or prescriptive recommendations to measure whether it’s working. The secondary benefit of diligently tracking the WWB project over an eight-year period is that we now have the rare [and lucky!] opportunity to examine a collaborative decision-making process empirically on a much larger scale than is normally seen in construction or any other industry.

    This may indeed be one of the few cases where so many data points have been collected that making basic findings can be both quite easy and, ironically, a bit difficult. There is so much richness and quantity in the data set that data patterns are readily apparent and rarely subject to statistical anomalies. In smaller or “normal” size cases, i.e., those comprising fewer partnering meetings (measurement points), fewer participants (sample size) or fewer objects of measurement, the usual worry is that one or two outliers can easily skew not only the mean descriptive data but also the inferential statistics. Small size is obviously not an issue with the voluminous aggregated data on the WWB project, and in the rare instances when outliers do arise, there are clear reasons why. Conversely, a huge data set can be difficult to approach because of the urge to dig deeper into this rich source of data to identify more subtle findings. In other words, the data set may well hold much more knowledge than is presented in this article.

    Overall, what do these general findings mean? Before launching into that discussion, recall that the partnering process, as used on the WWB project, is both an early warning conflict prevention method as well as an in situ conflict-management process. The distinction between the two is a matter of timing. Early identification of potential problems can, when the time arises, allow them to be prevented or managed more effectively. Based on the results of the data analysis for collaboration presented above, we believe that a number of antecedent conditions and variables were likely developed early on in order for the conflict prevention and management functions to operate as well as they did.

    The first condition or variable to consider is the context within which the project occurred. While context is not directly measured in the WWB partnering data, except indirectly under “Community Relationship” on some contracts, there is a strong possibility of external forces or actors impacting the process (for more information on external control, see Pfeffer & Salincik, 1978). The measurement of an external environment is a tough undertaking, even under ideal conditions and, as a result, most of the literature in this area is of a theoretical nature (cf. Emery, F. and Trist, E. 1965; also Baburoglu, O., 1988). Depending on the level and type of dynamics discussed, the literature describes a range of external environments going from placid (where no external forces or actors cause problems), to clustered (where allies clump together to meet a common foe head on) to disturbed (where the impact of the environment is less controlled by the parties, to turbulent (where the environment is so chaotic that most responses by combatants are maladaptive and only lead to more problems). Given the potential sources of potential conflict in scheduling, budget, dealing with the public and other issues, the Woodrow Wilson Bridge project arguably had the key ingredients of being undertaken in either a disturbed or a turbulent environment. With old WWB bridge presenting such a locally loathed bottleneck on the Capitol Beltway and the Interstate 95 corridor, the chances were high that that the project would generate many negative “above the fold” Washington Post headlines. But that didn’t happen, which begs the question why?

    This was no ordinary project. Two states, the District of Columbia and the Federal government were involved. This was the only Interstate highway bridge owned by the Federal government, and a flagship national bridge. Additionally, among the 200,000 daily travelers who use the bridge or live in its shadow are members of the U.S. House of Representatives and the U.S. Senate. Given the ambitious nature of the project, its high profile status and constant oversight by many governments and the media (print and broadcast), this was not the project on which to be a partner and have things go wrong. Another factor was the healthy relationship with the general-interest media that the WWB project leadership consciously cultivated. As a result of this proactive effort – itself a type of partnership – the media took a keen interest in the project – not so much looking for problems, but to highlight unusual aspects such as the unique design, human-interest stories, and other things that played well on the History and Discovery Channels’ documentaries on the WWB project.

    In this case, while there are no data to support this hypothesis, the high profile, high publicity nature of the project may have been an external force or intervening variable that helps explain, perhaps in some small way, why so many indicators came out so well. With so much attention being lavished on the project, it could be that, in one sense, this project was the largest example in modern history of the Hawthorne Effect (Landsberger, 1958)? [See Appendix.] Could this be a contextual layer not found in the partnering data that impacts the success of the project? Could this help explain how, given the countless sources of potential show-stoppers, the WWB project came out so well? We cannot empirically say one way or another, but we can offer this as a plausible counter explanation for the good results, alá Popper’s falsification process.

    The authors have mentioned occasionally throughout this article that there is room to consider the opposite time-ordered relationship between various partnering measures. However, one thing that we think is truly an antecedent condition or variable is the development of trust within the context of this project. While it cannot be analyzed quantitatively, trust may help explain the findings above, both the expected and the unexpected. Trust does not spring fully formed from a partnering workshop but more likely from consistent, transparent communication on the job, collaborative problem-solving in practice, a sense of interdependence among all partners, and perhaps even having the unstated feeling of being part of history. Trust, as least identity-based trust, is earned, and it is not a precondition of participation (Lewicki and Wiethoff, 2000). Without trust, people interact in a defensive mode. Communication by memorandum replaces informal discussion, and agreements are calculated more on exposure to risk than on wise and efficient means to ends.

    There are some important caveats to consider in weighing the observations from the WWB data set. One has to do with groupthink and/or self-fulfilling prophesy. It would not be surprising to find that, by meeting face-to-face nearly every month, partnering teams began to take on certain normative behaviors and started echoing each other’s sentiments. It could be that some over-reporting of positive results occurred (a classic “trip to Abilene” – see Harvey, 1974). With only one exception (contract VA-6/7), the rating results were presented anonymously, which may have served to reduce expectations to “go along” with the group. When individuals feel compelled to go along with the others, groupthink may set in. Conversely, when things are really going well a snowball effect tends to arise and people come to expect good things to happen – a nice self-fulfilling prophesy. Likewise, reaching deeper into speculative territory, perhaps some of the high scores could also represent a Hawthorne Effect, or they could stem from a collective sense of being a part of history.

    Another caveat is that some raters assuredly put more thought and effort into assigning ratings than others did. In performing an analysis of this type, the authors are effectively assuming that the number of raters who simply plugged in numbers so their bosses would not hector them for not responding is distributed evenly across the 19 contracts.

    The WWB project is unique; it set or broke engineering records, produced an elegant structure, and un-corked a traffic bottleneck that had bedeviled the region for decades. Considering the findings above, one might construct an unscientific formula for success: if, in a complex project, the right people work effectively together, at the right time and in the right place, then they have optimized the chances of reaching the right solutions/outcomes. While this is highly simplistic, it may well be to add that in cases like the WWB the right context or special circumstances, i.e., being part of a major or vital project or perhaps being a part of history, provides an added emphasis that instills a sense of pride and source of collaboration that provides even greater chances of success.

    Summary and Conclusions
    This article examined the large body of partnering rating data collected during eight-plus years of partnered construction contracts on the Woodrow Wilson Bridge program. The authors found that partnering efficacy, as measured by “collaboration,” was not predetermined by bid results or regional/national distinctions between construction contractors. The data showed that good partnering is strongly associated with team satisfaction with budget and schedule results. The authors assert that the self-reported scores for budget and schedule are an appropriate surrogate for “real” budget and schedule performance, since the latter are affected by so many external forces that any attempt to analyze them for partnering efficacy is unlikely to be any more persuasive.

    The data showed a strong association between good partnering (“collaboration”) and effective issue resolution. The authors believe that this is consistent with the hypothesis that effective issue resolution results in positive budget and schedule outcomes. The common association among these indicators is not “proof” of the effectiveness of partnering. However, had the analysis showed negative correlation where these positive correlations were expected, enthusiasm for construction partnering would certainly have suffered a blow.

    Acknowledgements
    The authors wish to acknowledge the Maryland State Highway Administration and the Virginia Department of Transportation for access to the WWB partnering data and permission to publish this study. Special thanks go to Mr. Terry Garrett, the WWB partnering coordinator from late 2008 and hence, for his assistance in updating the partnering rating data through June 2009.


    References
    1. Anderson, L., Douglass, R., and Kaub, B. (2006). Anatomy of a Successful Partnering Program on a Megaproject.” Leadership and Management in Engineering, 6(3), 110-116.
    2. Anderson, L., and Polkinghorn, B. (2008). “Managing Conflict in Construction Megaprojects: Leadership and Third-Party Principles.” Conflict Resolution Quarterly, 26(2), 167-198.
    3. Baburoglu, Oguz, N. (1988). “The Vortical Environment: The Fifth in the Emery-Trist Levels of Organizational Environments.” Human Relations, 41(3), 181-210.
    4. Cohen, J. (1988). Statistical power analysis for the behavioral sciences (2nd edition). Erlbaum, Hillsdale, N.J.
    5. Emery, F.E. and Trist, E.L. (1965). “The Causal Texture of Organizational Environments.” Human Relations, 18(1), 21-32.
    6. Harvey, J. B. (1974). “The Abilene Paradox and other Meditations on Management.” Organizational Dynamics, 3(1), 63 and ff.
    7. Landsberger, H. A. (1958), Hawthorne Revisited, Cornell University Press, Ithaca, N.Y. 1958.
    8. Lewicki, R., and Wiethoff, C. (2000). “Trust, Trust Development, and Trust Repair.” The Handbook of Conflict Resolution: Theory and Practice, M. Deutsch and P. T. Coleman, eds., Jossey-Bass, San Francisco, Ca., Ch. 4.
    9. Lowe, Scott W. (1994). “An Examination of the Effectiveness of Partnering in Navy Construction Contracts.” MS thesis, University of Washington, Seattle, Wa.
    10. Pfeffer, Jeffrey and Gerald Salincik (1978) External Control Theory: A Resource Dependence Perspective. Harper and Row, New York.
    11. Polkinghorn, Brian, Robert La Chance and Haleigh La Chance. (2006), “An Analysis of the Maryland Department of Transportation State Highway Administration’s Partnering Program and Process.” Maryland Department of Transportation, State Highway Administration. (Internal report to MDSHA)
    12. Rogge, D., Griffith, A., and Hutchins, W. (2002). “Improving the Effectiveness of Partnering,” State Planning and Research Report No. 344, Oregon Department of Transportation and Federal Highway Administration, November 2002.
    13. Young, James (2009). Personal communication providing link to on-line resource, “Introduction to Partnering, ADOT Partnering Office,”
      http://www.azdot.gov/ccpartnerships/partnering/education/intro_to_partnering/index.htm
    Appendix
    In a review of old studies on worker productivity from the 1920s and 1930s at the Hawthorne Works, Henry Landsberger coined the term “Hawthorne Effect” to describe the phenomenon whereby workers who received attention, in this case the reactivity of researchers in their presence, demonstrated higher productivity. In other words, when people are the subject of others’ supportive observations and attention they tend to react to this condition by being more productive. Add this to the positive reports that resulted, in terms of news reports and visits by VIPs to the WWB construction site, and conditions were ripe for the Hawthorne Effect to arise on this project.



    1 Larry Anderson, P.E., is a Senior Program Manager with MBP, Inc., and coordinated the partnering on the Woodrow Wilson Bridge project from 2001 through 2008. E-mail: LAnderson@mbpce.com; Mail: 10440 Little Patuxent Parkway, Suite 250, Columbia, MD 21044

    Professor Brian Polkinghorn, PhD, is Executive Director of Salisbury University’s Center for Conflict Resolution. E-mail: BDPolkinghorn@salisbury.edu; Mail: 1101 Camden Avenue, Salisbury, MD 21801

  • MBP © 2008 Legal Notice  |  Privacy Policy  |  Sitemap